Construction Material Price List in Ethiopia 2026

📊 CONMARET OFFICIAL DAILY CONSTRUCTION PRICE INDEX • ዕለታዊ የግንባታ እቃዎች የዋጋ ዝርዝር

የዛሬ የግንባታ እቃዎች የዋጋ ዝርዝር (Updated: 2026-11-23)

📞 የሽያጭ እና ፕሮፎርማ ክፍል፦ 0911 28 36 51 / 0911 28 36 71  |  ሁሉም ዋጋዎች 15% ቫት (VAT) ያካተቱ ናቸው።
የምርት ስም / Material Specification መለኪያ / Unit ከቫት በፊት (Excl. VAT) 15% ቫት (VAT) ጠቅላላ ዋጋ (Incl. 15% VAT) 📍 መጋዘን / Warehouse እርምጃ / Action
18mm Yellow Plywood — ቢጫ ፕላይዉድ Sheet (ፍሬ) ETB 5,173.91 ETB 776.09 ETB 5,950.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
28 ጌጅ ቃሊቲ ቆርቆሮ Meter (ሜትር) ETB 852.17 ETB 127.83 ETB 980.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
32 ጌጅ ኤጋ ቆርቆሮ | 32Gauge EGA Roofing Sheet Meter (ሜትር) ETB 808.70 ETB 121.30 ETB 930.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
6mm Cement Board | ሲሚንቶ ቦርድ Sheet (ፍሬ) ETB 10,000.00 ETB 1,500.00 ETB 11,500.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
8mm Cement Board – 1.22 × 2.44m Sheet (ፍሬ) ETB 12,200.00 ETB 1,830.00 ETB 14,030.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
8mm Magnesium Board (MgO Board) 1.22 × 2.44m – Price in Ethiopia Sheet (ፍሬ) ETB 5,000.00 ETB 750.00 ETB 5,750.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Adama Classic Tile Roofing Sheet — 28 Gauge Meter (ሜትር) ETB 1,286.96 ETB 193.04 ETB 1,480.00 📍 ዊንጌት አወሊያ አካባቢ 🛒 ይዘዙ 📋 ፕሮፎርማ
Africa Gypsum Sheet (ፍሬ) ETB 808.70 ETB 121.30 ETB 930.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Angle | አንግል የጂፕሰም ጠርዝ ፕሮፋይል Sheet (ፍሬ) ETB 295.65 ETB 44.35 ETB 340.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
APP Waterproofing Membrane Roll – Torch-on Bituminous Waterproofing Sheet (ፍሬ) ETB 13,500.00 ETB 2,025.00 ETB 15,525.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Armstrong Ceiling Unit (ፍሬ) ETB 2,391.30 ETB 358.70 ETB 2,750.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Brown Stone-Coated Roofing Tile – Decra Type Meter (ሜትር) ETB 1,434.78 ETB 215.22 ETB 1,650.00 📍 ዊንጌት አወሊያ አካባቢ 🛒 ይዘዙ 📋 ፕሮፎርማ
Buhi & Laminated Plywood 18mm | ቡሂ እና ላሚኔትድ ፕላይውድ sheet ETB 4,956.52 ETB 743.48 ETB 5,700.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Buhi Plywood 18mm | ቡሂ ፕላይዉድ 18ሚሜ Sheet (ፍሬ) ETB 5,990.00 ETB 898.50 ETB 6,888.50 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Cement Board & Magnesium Board | ሲሚንቶ እና ማግኒዢየም ቦርድ sheet ETB 8,695.65 ETB 1,304.35 ETB 10,000.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
CGI roofing sheet Meter (ሜትር) ETB 843.48 ETB 126.52 ETB 970.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Channel | ቻናል የጂፕሰም ፍሬም Sheet (ፍሬ) ETB 330.43 ETB 49.57 ETB 380.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
CHARLES & RAY EAMES, 1956 Unit (ፍሬ) ETB 39.13 ETB 5.87 ETB 45.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
CHARLES & RAY EAMES, 1956 Unit (ፍሬ) ETB 39.13 ETB 5.87 ETB 45.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Construction chemical Unit (ፍሬ) ETB 3,043.48 ETB 456.52 ETB 3,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Construction material Unit (ፍሬ) ETB 5,565.22 ETB 834.78 ETB 6,400.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Dangote Cement Quintal (ኩንታል) ETB 1,721.74 ETB 258.26 ETB 1,980.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Debre Birhan Plywood 18mm | ደብረ ብርሃን ፕላይዉድ 18ሚሜ Sheet (ፍሬ) ETB 5,200.00 ETB 780.00 ETB 5,980.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Decra Stone-Coated Roofing Sheet (ፍሬ) ETB 1,869.57 ETB 280.43 ETB 2,150.00 📍 ዊንጌት አወሊያ አካባቢ 🛒 ይዘዙ 📋 ፕሮፎርማ
Derba Cement Quintal (ኩንታል) ETB 1,513.04 ETB 226.96 ETB 1,740.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Driveway-Interlocking-Pavers Unit (ፍሬ) ETB 686.96 ETB 103.04 ETB 790.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA 500 PPGI Roofing Sheet Meter (ሜትር) ETB 765.22 ETB 114.78 ETB 880.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA 500 PPGI Roofing Sheet Meter (ሜትር) ETB 913.04 ETB 136.96 ETB 1,050.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA 500 PPGI Roofing Sheet Meter (ሜትር) ETB 1,200.00 ETB 180.00 ETB 1,380.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA 500 Trapezoidal Roofing Sheet – Coloured Metal Roofing Meter (ሜትር) ETB 765.22 ETB 114.78 ETB 880.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA 500 Trapezoidal Roofing Sheet – Coloured Metal Roofing Meter (ሜትር) ETB 1,182.61 ETB 177.39 ETB 1,360.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Ega Gray Color Meter (ሜትር) ETB 834.78 ETB 125.22 ETB 960.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA Grey Color — 3 mm / 4 mm Meter (ሜትር) ETB 773.91 ETB 116.09 ETB 890.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
EGA Red Color Meter (ሜትር) ETB 808.70 ETB 121.30 ETB 930.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
elevator-cladding Unit (ፍሬ) ETB 73,478.26 ETB 11,021.74 ETB 84,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Flat-Bar Unit (ፍሬ) ETB 113.04 ETB 16.96 ETB 130.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
floor-tiles Unit (ፍሬ) ETB 1,826.09 ETB 273.91 ETB 2,100.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
flush-tanks Unit (ፍሬ) ETB 5,217.39 ETB 782.61 ETB 6,000.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Formwork Plywood 18mm (1.22×2.44m) | የኮንስትራክሽን ፕላይውድ 18ሚሜ sheet ETB 7,391.30 ETB 1,108.70 ETB 8,500.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Galvanized Corrugated Roofing Sheet – 28G, 30G & 32G Meter (ሜትር) ETB 852.17 ETB 127.83 ETB 980.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Galvanized Corrugated Roofing Sheet – 28G, 30G & 32G Meter (ሜትር) ETB 1,113.04 ETB 166.96 ETB 1,280.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
GM Gypsum boared Sheet (ፍሬ) ETB 1,913.04 ETB 286.96 ETB 2,200.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
GM Gypsum boared Sheet (ፍሬ) ETB 1,913.04 ETB 286.96 ETB 2,200.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Granite ግራናይት Unit (ፍሬ) ETB 7,391.30 ETB 1,108.70 ETB 8,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
gravel Unit (ፍሬ) ETB 20,869.57 ETB 3,130.43 ETB 24,000.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Green Laminated Plywood 18mm (Grade 1) | አረንጓዴ ላሚኔትድ ፕላይውድ 18ሚሜ sheet ETB 7,652.17 ETB 1,147.83 ETB 8,800.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Gypsum Blocks – Fire-Resistant Partition Material Sheet (ፍሬ) ETB 721.74 ETB 108.26 ETB 830.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Gypsum Board | የጂፕሰም ቦርድ Sheet (ፍሬ) ETB 1,695.65 ETB 254.35 ETB 1,950.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Hardboard(Phyist) Sheet (ፍሬ) ETB 400.00 ETB 60.00 ETB 460.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
hi test Unit (ፍሬ) ETB 46.09 ETB 6.91 ETB 53.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
kitchen-countertops-cheat-sheet Unit (ፍሬ) ETB 7,391.30 ETB 1,108.70 ETB 8,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
kitchen-sink Unit (ፍሬ) ETB 7,826.09 ETB 1,173.91 ETB 9,000.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
knauf gypsum board Sheet (ፍሬ) ETB 2,695.65 ETB 404.35 ETB 3,100.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Laminate MDF 18mm | ላሚኔት MDF 18ሚሜ Sheet (ፍሬ) ETB 5,600.00 ETB 840.00 ETB 6,440.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MAECENAS IACULIS Unit (ፍሬ) ETB 1,956.52 ETB 293.48 ETB 2,250.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Adesilex P9 Grey Tile Adhesive (25kg) Unit (ፍሬ) ETB 1,350.00 ETB 202.50 ETB 1,552.50 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Adesilex P9 White Tile Adhesive (25kg) Unit (ፍሬ) ETB 1,350.00 ETB 202.50 ETB 1,552.50 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Epojet LV Two-Component Epoxy Resin for Injection (4kg Set) Unit (ፍሬ) ETB 15,000.00 ETB 2,250.00 ETB 17,250.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Idrostop PVC BIC ME 20 Waterstop (15m Roll) Unit (ፍሬ) ETB 18,521.74 ETB 2,778.26 ETB 21,300.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Keracolor FF 100 White Tile Grout (5kg) Unit (ፍሬ) ETB 521.74 ETB 78.26 ETB 600.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Keracolor FF 113 Cement Grey Tile Grout (5kg) Quintal (ኩንታል) ETB 521.74 ETB 78.26 ETB 600.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Keracolor FF 132 Beige Tile Grout (5kg) Unit (ፍሬ) ETB 521.74 ETB 78.26 ETB 600.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Keraflex Maxi S1 (N) Zero White (25kg) Unit (ፍሬ) ETB 1,295.65 ETB 194.35 ETB 1,490.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Mapefill GP-ME Non-Shrink Grout (25kg) Unit (ፍሬ) ETB 1,080.00 ETB 162.00 ETB 1,242.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Mapegrout Me05 Structural Repair Mortar (25kg) Unit (ፍሬ) ETB 2,200.00 ETB 330.00 ETB 2,530.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Mapegrout T60 ME Fiber-Reinforced Mortar (25kg) Unit (ፍሬ) ETB 1,400.00 ETB 210.00 ETB 1,610.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Mapelastic Smart Two-Component Waterproofing Mortar (30kg Set) Sheet (ፍሬ) ETB 9,250.00 ETB 1,387.50 ETB 10,637.50 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Mapenet 150 Alkali-Resistant Fiberglass Mesh (1x50m Roll) Unit (ፍሬ) ETB 10,000.00 ETB 1,500.00 ETB 11,500.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Planicrete Synthetic Rubber Latex Bonding Agent (25kg) Unit (ፍሬ) ETB 12,000.00 ETB 1,800.00 ETB 13,800.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Ultra Color Plus 100 White ALU Bag (5kg) Unit (ፍሬ) ETB 1,700.00 ETB 255.00 ETB 1,955.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
MAPEI Ultracolor Plus Anti-Efflorescence Tile Grout & Filler (5kg) Unit (ፍሬ) ETB 1,000.00 ETB 150.00 ETB 1,150.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Mdf Sheet (ፍሬ) ETB 4,521.74 ETB 678.26 ETB 5,200.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 10 mm Oak Veener Sheet (ፍሬ) ETB 3,089.57 ETB 463.43 ETB 3,553.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 10 Raw (ያለበሰ) Sheet (ፍሬ) ETB 2,473.91 ETB 371.09 ETB 2,845.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 18 mm Laminated Sheet (ፍሬ) ETB 5,000.00 ETB 750.00 ETB 5,750.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 18 mm Oak Veener Sheet (ፍሬ) ETB 3,478.26 ETB 521.74 ETB 4,000.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 3 mm Laminated Sheet (ፍሬ) ETB 1,160.87 ETB 174.13 ETB 1,335.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 6 mm Lamimated Sheet (ፍሬ) ETB 1,847.83 ETB 277.17 ETB 2,125.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 6 mm NV oak Veener Sheet (ፍሬ) ETB 2,285.22 ETB 342.78 ETB 2,628.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF 8 mm Raw (ያለበሰ) Sheet (ፍሬ) ETB 1,660.87 ETB 249.13 ETB 1,910.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
MDF Raw 18 mm 3990 Sheet (ፍሬ) ETB 4,339.13 ETB 650.87 ETB 4,990.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Metal Roof Ridge Cap – Step Roofing Accessory Meter (ሜትር) ETB 652.17 ETB 97.83 ETB 750.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
mgo-boared Unit (ፍሬ) ETB 3,043.48 ETB 456.52 ETB 3,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 320.00 ETB 48.00 ETB 368.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 400.00 ETB 60.00 ETB 460.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 565.22 ETB 84.78 ETB 650.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 700.00 ETB 105.00 ETB 805.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 1,000.00 ETB 150.00 ETB 1,150.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Morale Construction Timber | ሞራሌ Unit (ፍሬ) ETB 1,764.35 ETB 264.65 ETB 2,029.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
National Cement Quintal (ኩንታል) ETB 1,617.39 ETB 242.61 ETB 1,860.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Omega / Omer | ኦሜጋ የጂፕሰም ፕሮፋይል Sheet (ፍሬ) ETB 608.70 ETB 91.30 ETB 700.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Our Premium Granite Collection Unit (ፍሬ) ETB 7,217.39 ETB 1,082.61 ETB 8,300.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Our Premium Granite Collection Unit (ፍሬ) ETB 7,217.39 ETB 1,082.61 ETB 8,300.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Plywood Sheet (ፍሬ) ETB 6,521.74 ETB 978.26 ETB 7,500.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Plywood 18mm & MDF Boards | ፕላይውድ እና ኤምዲኤፍ sheet ETB 5,565.22 ETB 834.78 ETB 6,400.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
plywood 18mm&mdf Sheet (ፍሬ) ETB 6,521.74 ETB 978.26 ETB 7,500.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Power blue nile wire 1.5 Unit (ፍሬ) ETB 1,695.65 ETB 254.35 ETB 1,950.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
PVC 60×60 Ceiling Panel | PVC 60×60 የጣሪያ ፓነል Unit (ፍሬ) ETB 1,652.17 ETB 247.83 ETB 1,900.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
PVC GYPSUM LAMINED Waterproof Ceiling TILEs {60X60} Sheet (ፍሬ) ETB 826.09 ETB 123.91 ETB 950.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Raw MDF 18mm | ራው MDF 18ሚሜ Sheet (ፍሬ) ETB 4,500.00 ETB 675.00 ETB 5,175.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Rebar Dia 10mm 12m Bar (ቤርጋ) ETB 860.87 ETB 129.13 ETB 990.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Rebar Dia 12mm 12m Bar (ቤርጋ) ETB 1,239.13 ETB 185.87 ETB 1,425.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Rebar Dia 14mm 12m Bar (ቤርጋ) ETB 1,691.30 ETB 253.70 ETB 1,945.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Rebar Dia 16mm 12m Bar (ቤርጋ) ETB 2,208.70 ETB 331.30 ETB 2,540.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Rebar Dia 8mm 12m Bar (ቤርጋ) ETB 547.83 ETB 82.17 ETB 630.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Reinforcement Bat 12m Bar (ቤርጋ) ETB 747.83 ETB 112.17 ETB 860.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Reinforcement Bat 12m Bar (ቤርጋ) ETB 1,173.91 ETB 176.09 ETB 1,350.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x10mm Unit (ፍሬ) ETB 34,347.83 ETB 5,152.17 ETB 39,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x20mm Unit (ፍሬ) ETB 66,000.00 ETB 9,900.00 ETB 75,900.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x2mm Unit (ፍሬ) ETB 6,652.17 ETB 997.83 ETB 7,650.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x3mm Unit (ፍሬ) ETB 10,260.87 ETB 1,539.13 ETB 11,800.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x4mm Unit (ፍሬ) ETB 12,608.70 ETB 1,891.30 ETB 14,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x5mm Unit (ፍሬ) ETB 14,760.87 ETB 2,214.13 ETB 16,975.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 2000x1000x6mm Unit (ፍሬ) ETB 18,695.65 ETB 2,804.35 ETB 21,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Sheet Metal 3000x1500x3mm Unit (ፍሬ) ETB 20,608.70 ETB 3,091.30 ETB 23,700.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C20 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 17,800.00 ETB 2,670.00 ETB 20,470.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C25 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 18,200.00 ETB 2,730.00 ETB 20,930.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C30 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 19,200.00 ETB 2,880.00 ETB 22,080.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C35 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 19,700.00 ETB 2,955.00 ETB 22,655.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C40 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 20,600.00 ETB 3,090.00 ETB 23,690.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C45 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 21,500.00 ETB 3,225.00 ETB 24,725.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C5 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 13,000.00 ETB 1,950.00 ETB 14,950.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C50 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 22,400.00 ETB 3,360.00 ETB 25,760.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C55 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 23,400.00 ETB 3,510.00 ETB 26,910.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Shunyuan C60 Ready-Mix Concrete | ሬዲሚክስ ኮንክሪት Unit (ፍሬ) ETB 24,400.00 ETB 3,660.00 ETB 28,060.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Standard Construction Plywood 18mm | ፕላይውድ 18ሚሜ sheet ETB 6,695.65 ETB 1,004.35 ETB 7,700.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Steel Nails Unit (ፍሬ) ETB 756.52 ETB 113.48 ETB 870.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Summit nd aqua toilet set Unit (ፍሬ) ETB 14,347.83 ETB 2,152.17 ETB 16,500.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Transform Your Interior Spaces with Premium Gypsum Powder Sheet (ፍሬ) ETB 303.48 ETB 45.52 ETB 349.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Transform Your Interior Spaces with Premium Gypsum Powder Sheet (ፍሬ) ETB 303.48 ETB 45.52 ETB 349.00 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
Trapezoidal EGA Roofing Sheet | EGA ትራፔዞይዳል ቆርቆሮ Meter (ሜትር) ETB 765.22 ETB 114.78 ETB 880.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Trapezoidal EGA Roofing Sheet | EGA ትራፔዞይዳል ቆርቆሮ Meter (ሜትር) ETB 913.04 ETB 136.96 ETB 1,050.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Trapezoidal EGA Roofing Sheet | EGA ትራፔዞይዳል ቆርቆሮ Meter (ሜትር) ETB 1,200.00 ETB 180.00 ETB 1,380.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 968.70 ETB 145.30 ETB 1,114.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 1,513.91 ETB 227.09 ETB 1,741.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 2,180.00 ETB 327.00 ETB 2,507.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 2,966.96 ETB 445.04 ETB 3,412.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 3,874.78 ETB 581.22 ETB 4,456.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 6,054.78 ETB 908.22 ETB 6,963.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 8,719.13 ETB 1,307.87 ETB 10,027.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
Turkish Rebar 12m — 800 Ton New Stock 12m Bar (ቤርጋ) ETB 15,500.00 ETB 2,325.00 ETB 17,825.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
VESTIBULUM TEMPUS METUS Unit (ፍሬ) ETB 1,478.26 ETB 221.74 ETB 1,700.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
VESTIBULUM TEMPUS METUS Unit (ፍሬ) ETB 1,478.26 ETB 221.74 ETB 1,700.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
Yellow Buhi Plywood 18mm (1.22×2.44m) | ቢጫ ቡሂ ፕላይውድ 18ሚሜ sheet ETB 5,130.43 ETB 769.57 ETB 5,900.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ሞራሌ 4*5 ሻሽመኔ Unit (ፍሬ) ETB 504.35 ETB 75.65 ETB 580.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ሞራሌ 7*5 ሻሸመኔ Unit (ፍሬ) ETB 669.57 ETB 100.43 ETB 770.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ቢጫ ፕላይውድ 18 ሚሊሜትር – 1.22×2.44 ሜትር Sheet (ፍሬ) ETB 5,608.70 ETB 841.30 ETB 6,450.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ባለ 20 ብረት 12m Bar (ቤርጋ) ETB 4,239.13 ETB 635.87 ETB 4,875.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
ብሪሊያንት ጂብሰም 25 ኪ.ግ | Brilliant Gypsum – ኮንማርት Sheet (ፍሬ) ETB 730.00 ETB 109.50 ETB 839.50 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
ነጭ ፑቲ 25 ኪ.ግ | White Putty – ኮንማርት Unit (ፍሬ) ETB 2,530.00 ETB 379.50 ETB 2,909.50 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
አረንጓዴ Laminated Plywood 18 ሚሊሜትር – 1.22×2.44 ሜትር Sheet (ፍሬ) ETB 7,565.22 ETB 1,134.78 ETB 8,700.00 📍 ሰሚት ጋር እና አውቶብስ ተራ መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
አሪቲ 28 ጌጅ ቆርቆሮ Meter (ሜትር) ETB 1,130.43 ETB 169.57 ETB 1,300.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 10 ሚሊ | Abyssinia 10mm Rebar 12m Bar (ቤርጋ) ETB 1,341.00 ETB 201.15 ETB 1,542.15 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 12 ሚሊ | Abyssinia 12mm Rebar 12m Bar (ቤርጋ) ETB 1,931.00 ETB 289.65 ETB 2,220.65 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 14 ሚሊ | Abyssinia 14mm Rebar 12m Bar (ቤርጋ) ETB 2,628.00 ETB 394.20 ETB 3,022.20 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 16 ሚሊ | Abyssinia 16mm Rebar 12m Bar (ቤርጋ) ETB 3,432.00 ETB 514.80 ETB 3,946.80 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 20 ሚሊ | Abyssinia 20mm Rebar 12m Bar (ቤርጋ) ETB 5,425.00 ETB 813.75 ETB 6,238.75 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 24 ሚሊ | Abyssinia 24mm Rebar 12m Bar (ቤርጋ) ETB 8,221.00 ETB 1,233.15 ETB 9,454.15 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አቢሲኒያ ግሬድ 75 ብረት 8 ሚሊ | Abyssinia 8mm Rebar 12m Bar (ቤርጋ) ETB 863.00 ETB 129.45 ETB 992.45 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
አዳማ ታየልስ የቪላቤት ቆርቆሮ Meter (ሜትር) ETB 1,260.87 ETB 189.13 ETB 1,450.00 📍 ዊንጌት አወሊያ አካባቢ 🛒 ይዘዙ 📋 ፕሮፎርማ
አፍሪካ ጂብሰም 25 ኪ.ግ | Africa Gypsum 25kg – ኮንማርት Sheet (ፍሬ) ETB 870.00 ETB 130.50 ETB 1,000.50 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
ኤም ሲ አድሂሲቭ 25 ኪ.ግ | M C Adhesive – ኮንማርት Unit (ፍሬ) ETB 1,430.00 ETB 214.50 ETB 1,644.50 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ኤም ጂ ጂብሰም 25 ኪ.ግ | M G Gypsum 25kg – ኮንማርት Sheet (ፍሬ) ETB 850.00 ETB 127.50 ETB 977.50 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
ኤጋ ቆርቆሮ በ30 ጌጅ Meter (ሜትር) ETB 1,069.57 ETB 160.43 ETB 1,230.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ኤጋ በ28 ጌጅ Meter (ሜትር) ETB 1,130.43 ETB 169.57 ETB 1,300.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው ብረቶች Unit (ፍሬ) ETB 200.00 ETB 30.00 ETB 230.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው ብረቶች Unit (ፍሬ) ETB 200.00 ETB 30.00 ETB 230.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 2,023.01 ETB 303.45 ETB 2,326.46 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 2,599.75 ETB 389.96 ETB 2,989.71 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 3,014.01 ETB 452.10 ETB 3,466.11 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 3,748.29 ETB 562.24 ETB 4,310.53 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 3,879.93 ETB 581.99 ETB 4,461.92 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 4,831.45 ETB 724.72 ETB 5,556.17 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 4,955.00 ETB 743.25 ETB 5,698.25 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 6,140.35 ETB 921.05 ETB 7,061.40 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 6,400.90 ETB 960.14 ETB 7,361.04 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 7,304.35 ETB 1,095.65 ETB 8,400.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 7,949.84 ETB 1,192.48 ETB 9,142.32 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 9,478.26 ETB 1,421.74 ETB 10,900.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 9,568.27 ETB 1,435.24 ETB 11,003.51 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የምናቀርባቸው የምርት አይነቶች Unit (ፍሬ) ETB 12,473.56 ETB 1,871.03 ETB 14,344.59 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
የቪላ ቤት ቆርቆሮ Meter (ሜትር) ETB 939.13 ETB 140.87 ETB 1,080.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
የቱርክ ብረት በሚገርም ቅናሽ 12m Bar (ቤርጋ) ETB 115.65 ETB 17.35 ETB 133.00 📍 ፉሪ ሃጫሉ አደባባይ ጋር 🛒 ይዘዙ 📋 ፕሮፎርማ
የኤጋ 500 ቆርቆሮ – 28 ጌጅ | EGA 500 Roofing Sheet Sheet (ፍሬ) ETB 3,547.83 ETB 532.17 ETB 4,080.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
የኤጋ 500 ቆርቆሮ – 28 ጌጅ | EGA 500 Roofing Sheet Sheet (ፍሬ) ETB 7,095.65 ETB 1,064.35 ETB 8,160.00 📍 ተክለሃይማኖት መርካቶ 🛒 ይዘዙ 📋 ፕሮፎርማ
ዲ ኤች ገዳ አድሂሲቭ 25 ኪ.ግ | D H Geda Adhesive – ኮንማርት Unit (ፍሬ) ETB 1,480.00 ETB 222.00 ETB 1,702.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ጄቦልት Unit (ፍሬ) ETB 86.96 ETB 13.04 ETB 100.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ግራጫ ፑቲ 25 ኪ.ግ | Grey Putty – ኮንማርት Unit (ፍሬ) ETB 1,480.00 ETB 222.00 ETB 1,702.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ፍላት አይረን Flat Iron Unit (ፍሬ) ETB 217.39 ETB 32.61 ETB 250.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ፕራይም ተገጣጣሚ አጥር Unit (ፍሬ) ETB 1,608.70 ETB 241.30 ETB 1,850.00 📍 ቃሊቲ እና መርካቶ ማዕከላዊ መጋዘን 🛒 ይዘዙ 📋 ፕሮፎርማ
ፕራይም ኮት 25 ኪ.ግ | Prime Coat – ኮንማርት Unit (ፍሬ) ETB 890.00 ETB 133.50 ETB 1,023.50 📍 ጃክሮስ ገርጂ 🛒 ይዘዙ 📋 ፕሮፎርማ
ADDIS ABABA • ETHIOPIA

Construction material prices in Ethiopia

Find the right reference. Understand the unit. Build a better budget.

የግንባታ ዋጋዎችን በምድብ ይመልከቱ፤ መለኪያውን ያረጋግጡ።

Know what the price covers. Material selling prices, construction work rates, labour and equipment hire are separate. This is a 2018 E.C. Q4 reference, not a live supplier quotation. The material table excludes VAT and states loading, unloading and transportation are included. Confirm current supply terms with Conmart.
23organized categories
53source document pages
232digitized & visually checked rates
ETBEthiopian birr · original units
SOURCE-BASED PRICE DIRECTORY

All checked prices

Compare the right specification and unit. Open a category to read its complete source tables.

232 checked rates
Checked reference prices in Ethiopian birr. Units and source pages are shown for each entry.
Material / specificationReference rateEstimate
Cement (PPC)Cement · Material · Excl. VATSource: PDF p. 49 ↗2,100.00ETB / quintal
Cement (OPC)Cement · Material · Excl. VATSource: PDF p. 49 ↗2,400.00ETB / quintal
Local Rebar Grade 75 (Ethiopia)Rebar supply · Material · Excl. VATSource: PDF p. 49 ↗200.00ETB / kg
Imported Rebar Grade 75Rebar supply · Material · Excl. VATSource: PDF p. 49 ↗205.00ETB / kg
SandSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗6,250.00ETB / m³
Gravel 02Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗5,625.00ETB / m³
FINO (01)Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗5,727.00ETB / m³
FINO (00)Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗6,562.00ETB / m³
Red ashSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗2,717.00ETB / m³
StoneSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗2,850.00ETB / m³
BrickSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗30.00ETB / piece
Stone for hardcoreSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗2,196.00ETB / m³
Selected material — up to 5 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗729.50ETB / m³
Selected material — up to 10 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗1,042.00ETB / m³
Selected material — up to 15 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗1,354.50ETB / m³
Selected material — up to 20 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗1,667.00ETB / m³
Local Granite flooring (1:3), 2 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗7,300.00ETB / m²
Local Granite flooring (1:3), 3 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗7,500.00ETB / m²
Local Marble flooring (1:3), 2 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗6,600.00ETB / m²
Local Marble flooring (1:3), 3 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗6,750.00ETB / m²
Bar bender assistantLabour by trade · LabourSource: PDF p. 50 ↗90.00ETB / hour
Bar benderLabour by trade · LabourSource: PDF p. 50 ↗134.93ETB / hour
Carpenter assistantLabour by trade · LabourSource: PDF p. 50 ↗97.61ETB / hour
CarpenterLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
ChislerLabour by trade · LabourSource: PDF p. 50 ↗93.56ETB / hour
DL (source abbreviation)Labour by trade · LabourSource: PDF p. 50 ↗80.00ETB / hour
Electrician helperLabour by trade · LabourSource: PDF p. 50 ↗117.90ETB / hour
ElectricianLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
ForemanLabour by trade · LabourSource: PDF p. 50 ↗161.91ETB / hour
Gang chiefLabour by trade · LabourSource: PDF p. 50 ↗129.01ETB / hour
GlazerLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
Mason assistantLabour by trade · LabourSource: PDF p. 50 ↗90.00ETB / hour
MasonLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
Mixer operatorLabour by trade · LabourSource: PDF p. 50 ↗63.10ETB / hour
Painter assistantLabour by trade · LabourSource: PDF p. 50 ↗82.51ETB / hour
PainterLabour by trade · LabourSource: PDF p. 50 ↗120.00ETB / hour
Plasterer assistantLabour by trade · LabourSource: PDF p. 50 ↗84.26ETB / hour
PlastererLabour by trade · LabourSource: PDF p. 50 ↗126.19ETB / hour
Plumber helperLabour by trade · LabourSource: PDF p. 50 ↗92.41ETB / hour
PlumberLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
Tiler assistantLabour by trade · LabourSource: PDF p. 50 ↗107.46ETB / hour
TilerLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
Time keeperLabour by trade · LabourSource: PDF p. 50 ↗93.07ETB / hour
Truck driverLabour by trade · LabourSource: PDF p. 50 ↗119.90ETB / hour
Equipment operator ILabour by trade · LabourSource: PDF p. 50 ↗89.05ETB / hour
Equipment operator IILabour by trade · LabourSource: PDF p. 50 ↗83.25ETB / hour
Equipment operator IIILabour by trade · LabourSource: PDF p. 50 ↗78.82ETB / hour
Vibrator operatorLabour by trade · LabourSource: PDF p. 50 ↗124.87ETB / hour
Light vehicle driver ILabour by trade · LabourSource: PDF p. 50 ↗97.56ETB / hour
SurveyorLabour by trade · LabourSource: PDF p. 50 ↗125.00ETB / hour
WelderLabour by trade · LabourSource: PDF p. 50 ↗180.00ETB / hour
Welder assistantLabour by trade · LabourSource: PDF p. 51 ↗80.65ETB / hour
Aluminium workerLabour by trade · LabourSource: PDF p. 51 ↗180.00ETB / hour
Aluminium worker assistantLabour by trade · LabourSource: PDF p. 51 ↗81.89ETB / hour
Mud workerLabour by trade · LabourSource: PDF p. 51 ↗81.29ETB / hour
Truck 16 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗7,009.20ETB / hour
Truck 9 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗2,560.36ETB / hour
Truck 13 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗3,251.20ETB / hour
CompactorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗678.05ETB / hour
Wheel loader 200 HP (1.5–2.5 m³)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗6,297.13ETB / hour
Dozer 300 HP (D7R)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗9,610.35ETB / hour
Dozer D7R with ripperEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗10,060.35ETB / hour
Dozer (200–250 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗8,867.34ETB / hour
Excavator (200 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗8,560.35ETB / hour
Excavator (200 HP) with ripperEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗9,131.04ETB / hour
Backhoe excavator (120 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗6,560.35ETB / hour
Grader (120–150 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗7,560.35ETB / hour
Roller (8–10 ton)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗4,304.60ETB / hour
Water truck 13,000 litresEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗4,195.20ETB / hour
Air compressorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗3,657.34ETB / hour
Hand jack hammer (electrical)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗264.00ETB / hour
Wagon drillerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗9,465.22ETB / hour
Small vehicle (pickup 4WD)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗1,251.54ETB / hour
Asphalt distributorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗5,166.50ETB / hour
Stationary heaterEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗3,451.86ETB / hour
Power broomEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗2,380.24ETB / hour
Asphalt plantEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗51,858.19ETB / hour
Asphalt paverEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗11,433.22ETB / hour
Pneumatic rollerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗4,133.65ETB / hour
Water tankerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗38.05ETB / hour
Dump truck 16 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗2,784.53ETB / hour
Crushing plant 75 tonEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗19,952.80ETB / hour
Centrifugal water pumpEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗499.85ETB / hour
Generator (45 kW)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗935.89ETB / hour
Mobile craneEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗7,609.20ETB / hour
Concrete mixer (300 litres)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗519.22ETB / hour
Concrete mixer truckEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗3,098.82ETB / hour
Concrete vibratorEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗266.09ETB / hour
Hand tamperEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗110.47ETB / hour
Pipe mouldEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗24.85ETB / hour
Painting machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗1,253.57ETB / hour
Hand drillEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗20.71ETB / hour
Gear machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗34.52ETB / hour
GrinderEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗34.52ETB / hour
Cutting disc (diameter 180)Equipment & machinery rental · EquipmentSource: PDF p. 53 ↗162.00ETB / hour
ScaffoldingEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗117.60ETB / hour
Sledge hammerEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗6.28ETB / hour
ToolsEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗14.40ETB / hour
Set of toolsEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗22.80ETB / hour
Surveying instrumentEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗129.24ETB / hour
Welding machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗101.20ETB / hour
Hydraulic truck crane, 20–25 tonEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗5,383.58ETB / hour
Winch 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗251.04ETB / hour
Winch single phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗188.28ETB / hour
Generator 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗502.08ETB / hour
Generator single phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗313.80ETB / hour
Generator for winch 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗403.92ETB / hour
Local Grade 75 rebar work, 6 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗246.97ETB / kg
Local Grade 75 rebar work, 8 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗242.06ETB / kg
Local Grade 75 rebar work, 10 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗242.06ETB / kg
Local Grade 75 rebar work, 12 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 14 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 16 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 20 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 24 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 32 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗238.74ETB / kg
Local Grade 75 rebar work, 6 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗249.12ETB / kg
Local Grade 75 rebar work, 8 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗249.12ETB / kg
Local Grade 75 rebar work, 10 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗249.12ETB / kg
Local Grade 75 rebar work, 12 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Local Grade 75 rebar work, 14 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Local Grade 75 rebar work, 16 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Local Grade 75 rebar work, 20 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Local Grade 75 rebar work, 24 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Local Grade 75 rebar work, 32 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗241.72ETB / kg
Imported Grade 75 rebar work, 8 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗252.12ETB / kg
Imported Grade 75 rebar work, 10 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗252.12ETB / kg
Imported Grade 75 rebar work, 12 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 14 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 16 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 20 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 24 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 30 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 32 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗243.89ETB / kg
Imported Grade 75 rebar work, 8 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗260.35ETB / kg
Imported Grade 75 rebar work, 10 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗260.35ETB / kg
Imported Grade 75 rebar work, 12 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Imported Grade 75 rebar work, 14 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Imported Grade 75 rebar work, 16 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Imported Grade 75 rebar work, 20 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Imported Grade 75 rebar work, 24 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗251.95ETB / kg
Imported Grade 75 rebar work, 30 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Imported Grade 75 rebar work, 32 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗246.87ETB / kg
Galvanized EGA 300 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,596.25ETB / m²
Galvanized EGA 300 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,785.51ETB / m²
Galvanized EGA 300 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,958.45ETB / m²
Galvanized EGA 300 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,135.55ETB / m²
Galvanized EGA 300 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,385.35ETB / m²
Galvanized EGA 300 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,632.49ETB / m²
Galvanized EGA 300 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,863.96ETB / m²
Galvanized EGA 300 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,107.64ETB / m²
Galvanized EGA 400 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,780.73ETB / m²
Galvanized EGA 400 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,987.74ETB / m²
Galvanized EGA 400 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,217.70ETB / m²
Galvanized EGA 400 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,430.31ETB / m²
Galvanized EGA 400 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,623.64ETB / m²
Galvanized EGA 400 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,847.72ETB / m²
Galvanized EGA 400 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,071.13ETB / m²
Galvanized EGA 400 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,264.50ETB / m²
Galvanized EGA 500 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,846.07ETB / m²
Galvanized EGA 500 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,116.70ETB / m²
Galvanized EGA 500 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,300.15ETB / m²
Galvanized EGA 500 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,523.61ETB / m²
Galvanized EGA 500 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,731.78ETB / m²
Galvanized EGA 500 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,935.84ETB / m²
Galvanized EGA 500 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,213.53ETB / m²
Galvanized EGA 500 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,488.80ETB / m²
Galvanized EGA 600 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,915.24ETB / m²
Galvanized EGA 600 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,110.72ETB / m²
Galvanized EGA 600 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,313.65ETB / m²
Galvanized EGA 600 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,543.02ETB / m²
Galvanized EGA 600 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,756.42ETB / m²
Galvanized EGA 600 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,977.88ETB / m²
Galvanized EGA 600 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,263.52ETB / m²
Galvanized EGA 600 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,584.72ETB / m²
Galvanized EGA 700 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗1,997.42ETB / m²
Galvanized EGA 700 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,153.62ETB / m²
Galvanized EGA 700 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,329.62ETB / m²
Galvanized EGA 700 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,631.07ETB / m²
Galvanized EGA 700 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,765.22ETB / m²
Galvanized EGA 700 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗2,988.52ETB / m²
Galvanized EGA 700 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,289.92ETB / m²
Galvanized EGA 700 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗3,601.22ETB / m²
EGA 0.4 mm (G28) coated roof coverRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,929.94ETB / m²
EGA 0.4 mm (G28) coated wall coverRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,754.90ETB / m²
EGA 0.4 mm (G28) coated wall with 10 cm vertical and 6 cm horizontal eucalyptus membersRoofing & rainwater goods · WorksSource: PDF p. 18 ↗2,022.07ETB / m²
Galvanized gutter G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗821.83ETB / linear m
Galvanized gutter G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗750.07ETB / linear m
Galvanized gutter G28, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗968.35ETB / linear m
Galvanized gutter G30, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗864.31ETB / linear m
Galvanized gutter G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,157.05ETB / linear m
Galvanized gutter G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗920.41ETB / linear m
Galvanized gutter G28, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,332.49ETB / linear m
Galvanized gutter G30, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,051.99ETB / linear m
Galvanized gutter G28, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,470.71ETB / linear m
Galvanized gutter G30, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗1,299.85ETB / linear m
Galvanized downpipe G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗854.07ETB / linear m
Galvanized downpipe G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗854.07ETB / linear m
Galvanized downpipe G28, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,012.90ETB / linear m
Galvanized downpipe G30, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗857.70ETB / linear m
Galvanized downpipe G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,077.46ETB / linear m
Galvanized downpipe G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,044.66ETB / linear m
Galvanized flashing G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,082.14ETB / linear m
Galvanized flashing G30, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,192.91ETB / linear m
Galvanized flashing G30, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,497.41ETB / linear m
Galvanized flashing G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,264.84ETB / linear m
Galvanized flashing G28, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,472.74ETB / linear m
Galvanized flashing G28, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,590.48ETB / linear m
Galvanized capping G28, developed length 25 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗620.78ETB / linear m
Galvanized capping G30, developed length 25 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗615.68ETB / linear m
Galvanized capping G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗856.77ETB / linear m
Galvanized capping G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗616.70ETB / linear m
Galvanized capping G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗865.58ETB / linear m
Galvanized capping G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗824.78ETB / linear m
Galvanized roof ridge G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗759.81ETB / linear m
Galvanized roof ridge G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗657.81ETB / linear m
Galvanized roof ridge G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗889.35ETB / linear m
Galvanized roof ridge G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗792.45ETB / linear m
PVC downpipe PN4, 75 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗469.41ETB / linear m
PVC downpipe PN4, 110 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗567.84ETB / linear m
PVC downpipe PN4, 160 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,019.08ETB / linear m
G28 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,370.13ETB / m²
G30 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,229.59ETB / m²
G32 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗997.16ETB / m²
G35 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗833.46ETB / m²
Aspesto roof cover with all necessary works (source wording)Roofing & rainwater goods · WorksSource: PDF p. 19 ↗847.68ETB / m²
Euro tile roof cover with all necessary worksRoofing & rainwater goods · WorksSource: PDF p. 19 ↗878.88ETB / m²
Grass roof cover with all necessary worksRoofing & rainwater goods · WorksSource: PDF p. 19 ↗825.13ETB / m²
Transparent fibre roof cover, corrugated, 2 mmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,257.17ETB / m²
G32 CIS roof with Shashemene Zigba purlin (4 × 5 cm)Roofing & rainwater goods · WorksSource: PDF p. 19 ↗1,412.24ETB / m²
Tsid timber cladding, 1 cm, for decorating roof purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗1,453.56ETB / m²
Lightweight concrete 1:2:5 for roofRoofing & rainwater goods · WorksSource: PDF p. 19 ↗15,754.06ETB / m³

Complete source tables

Every category includes its original PDF pages. Search and estimates use visually checked transcriptions; additional work rates remain available in the full source tables.

PDF page 6 ↗Printed page 1 · full original tablePDF page 7 ↗Printed page 2 · full original tablePDF page 8 ↗Printed page 3 · full original tablePDF page 9 ↗Printed page 4 · full original tablePDF page 10 ↗Printed page 5 · full original tablePDF page 11 ↗Printed page 6 · full original tablePDF page 12 ↗Printed page 7 · full original tablePDF page 13 ↗Printed page 8 · full original tablePDF page 14 ↗Printed page 9 · full original tablePDF page 15 ↗Printed page 10 · full original tablePDF page 16 ↗Printed page 11 · full original tablePDF page 17 ↗Printed page 12 · full original tablePDF page 18 ↗Printed page 13 · full original tablePDF page 19 ↗Printed page 14 · full original tablePDF page 20 ↗Printed page 15 · full original tablePDF page 21 ↗Printed page 16 · full original tablePDF page 22 ↗Printed page 17 · full original tablePDF page 23 ↗Printed page 18 · full original tablePDF page 24 ↗Printed page 19 · full original tablePDF page 25 ↗Printed page 20 · full original tablePDF page 26 ↗Printed page 21 · full original tablePDF page 27 ↗Printed page 22 · full original tablePDF page 28 ↗Printed page 23 · full original tablePDF page 29 ↗Printed page 24 · full original tablePDF page 30 ↗Printed page 25 · full original tablePDF page 31 ↗Printed page 26 · full original tablePDF page 32 ↗Printed page 27 · full original tablePDF page 33 ↗Printed page 28 · full original tablePDF page 34 ↗Printed page 29 · full original tablePDF page 35 ↗Printed page 30 · full original tablePDF page 36 ↗Printed page 31 · full original tablePDF page 37 ↗Printed page 32 · full original tablePDF page 38 ↗Printed page 33 · full original tablePDF page 39 ↗Printed page 34 · full original tablePDF page 40 ↗Printed page 35 · full original tablePDF page 41 ↗Printed page 36 · full original tablePDF page 42 ↗Printed page 37 · full original tablePDF page 43 ↗Printed page 38 · full original tablePDF page 44 ↗Printed page 39 · full original tablePDF page 45 ↗Printed page 40 · full original tablePDF page 46 ↗Printed page 41 · full original tablePDF page 47 ↗Printed page 42 · full original tablePDF page 48 ↗Printed page 43 · full original tablePDF page 49 ↗Printed page 44 · full original tablePDF page 50 ↗Printed page 45 · full original tablePDF page 51 ↗Printed page 46 · full original tablePDF page 52 ↗Printed page 47 · full original tablePDF page 53 ↗Printed page 48 · full original table
PLAN YOUR QUANTITIES

Your reference estimate

Add a checked rate with the + button. Quantities use the exact unit shown.

Your estimate is empty. Add materials or work items above.

Reference subtotal
0.00 ETB
Not a VAT calculation. No tax or delivery amount is added automatically.

Request current quote ↗
Budget reference only. Check that selected scopes do not overlap; for example, supply rebar and reinforcement work are separate reference types. No order is placed or message sent.

Before you use a rate

Are these current Conmart selling prices?

No. They are rates from the supplied Addis Ababa construction cost document for 2018 E.C. Q4. Request a current quote for availability, brand, specification and delivery terms.

Does “2018” mean Gregorian 2018?

The document uses the Ethiopian calendar and identifies the 2018 E.C. fourth quarter. The cover letter is dated 30/10/2018 E.C. The original period is retained to avoid confusion with Gregorian years.

Are VAT and transport included?

PDF page 49 explicitly says material selling prices are without VAT. Its note includes loading, unloading and transportation. Do not automatically apply that note to every work or hire rate. Confirm the relevant scope and tax treatment in your supplier quotation.

What is the difference between supply and work rates?

The material table gives local Grade 75 rebar at 200 ETB/kg. The separate reinforcement work table gives rates by diameter and structure. Similarly, roofing work per m² is different from a roofing sheet sold per running metre.

How should I read the units?

One quintal is 100 kg. m² means square metre; m³ means cubic metre; linear m means running metre. Labour and machinery tables are hourly. Preserve the source unit when entering quantities.

Why do some categories open original tables?

The source is scanned. Checked transcriptions are searchable and available for estimates. The complete source pages preserve all remaining rates, specifications and qualifications without publishing unverified OCR numbers.

CONMART · Build with clarity.
Source: Addis Ababa City Administration Design and Construction Works Bureau
2018 E.C. Q4 · 53-page supplied PDF