Construction Material Prices in Ethiopia 2026 — Source Reference
Construction material prices in Ethiopia
Find the right reference. Understand the unit. Build a better budget.
የግንባታ ዋጋዎችን በምድብ ይመልከቱ፤ መለኪያውን ያረጋግጡ።
All checked prices
Compare the right specification and unit. Open a category to read its complete source tables.
| Material / specification | Reference rate | Estimate |
|---|---|---|
| Cement (PPC)Cement · Material · Excl. VATSource: PDF p. 49 ↗ | 2,100.00ETB / quintal | |
| Cement (OPC)Cement · Material · Excl. VATSource: PDF p. 49 ↗ | 2,400.00ETB / quintal | |
| Local Rebar Grade 75 (Ethiopia)Rebar supply · Material · Excl. VATSource: PDF p. 49 ↗ | 200.00ETB / kg | |
| Imported Rebar Grade 75Rebar supply · Material · Excl. VATSource: PDF p. 49 ↗ | 205.00ETB / kg | |
| SandSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 6,250.00ETB / m³ | |
| Gravel 02Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 5,625.00ETB / m³ | |
| FINO (01)Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 5,727.00ETB / m³ | |
| FINO (00)Sand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 6,562.00ETB / m³ | |
| Red ashSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 2,717.00ETB / m³ | |
| StoneSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 2,850.00ETB / m³ | |
| BrickSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 30.00ETB / piece | |
| Stone for hardcoreSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 2,196.00ETB / m³ | |
| Selected material — up to 5 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 729.50ETB / m³ | |
| Selected material — up to 10 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 1,042.00ETB / m³ | |
| Selected material — up to 15 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 1,354.50ETB / m³ | |
| Selected material — up to 20 km from quarry to project siteSand, aggregates & blocks · Material · Excl. VATSource: PDF p. 49 ↗ | 1,667.00ETB / m³ | |
| Local Granite flooring (1:3), 2 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗ | 7,300.00ETB / m² | |
| Local Granite flooring (1:3), 3 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗ | 7,500.00ETB / m² | |
| Local Marble flooring (1:3), 2 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗ | 6,600.00ETB / m² | |
| Local Marble flooring (1:3), 3 cm thickMarble & granite supply · Material · Excl. VATSource: PDF p. 49 ↗ | 6,750.00ETB / m² | |
| Bar bender assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 90.00ETB / hour | |
| Bar benderLabour by trade · LabourSource: PDF p. 50 ↗ | 134.93ETB / hour | |
| Carpenter assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 97.61ETB / hour | |
| CarpenterLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| ChislerLabour by trade · LabourSource: PDF p. 50 ↗ | 93.56ETB / hour | |
| DL (source abbreviation)Labour by trade · LabourSource: PDF p. 50 ↗ | 80.00ETB / hour | |
| Electrician helperLabour by trade · LabourSource: PDF p. 50 ↗ | 117.90ETB / hour | |
| ElectricianLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| ForemanLabour by trade · LabourSource: PDF p. 50 ↗ | 161.91ETB / hour | |
| Gang chiefLabour by trade · LabourSource: PDF p. 50 ↗ | 129.01ETB / hour | |
| GlazerLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| Mason assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 90.00ETB / hour | |
| MasonLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| Mixer operatorLabour by trade · LabourSource: PDF p. 50 ↗ | 63.10ETB / hour | |
| Painter assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 82.51ETB / hour | |
| PainterLabour by trade · LabourSource: PDF p. 50 ↗ | 120.00ETB / hour | |
| Plasterer assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 84.26ETB / hour | |
| PlastererLabour by trade · LabourSource: PDF p. 50 ↗ | 126.19ETB / hour | |
| Plumber helperLabour by trade · LabourSource: PDF p. 50 ↗ | 92.41ETB / hour | |
| PlumberLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| Tiler assistantLabour by trade · LabourSource: PDF p. 50 ↗ | 107.46ETB / hour | |
| TilerLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| Time keeperLabour by trade · LabourSource: PDF p. 50 ↗ | 93.07ETB / hour | |
| Truck driverLabour by trade · LabourSource: PDF p. 50 ↗ | 119.90ETB / hour | |
| Equipment operator ILabour by trade · LabourSource: PDF p. 50 ↗ | 89.05ETB / hour | |
| Equipment operator IILabour by trade · LabourSource: PDF p. 50 ↗ | 83.25ETB / hour | |
| Equipment operator IIILabour by trade · LabourSource: PDF p. 50 ↗ | 78.82ETB / hour | |
| Vibrator operatorLabour by trade · LabourSource: PDF p. 50 ↗ | 124.87ETB / hour | |
| Light vehicle driver ILabour by trade · LabourSource: PDF p. 50 ↗ | 97.56ETB / hour | |
| SurveyorLabour by trade · LabourSource: PDF p. 50 ↗ | 125.00ETB / hour | |
| WelderLabour by trade · LabourSource: PDF p. 50 ↗ | 180.00ETB / hour | |
| Welder assistantLabour by trade · LabourSource: PDF p. 51 ↗ | 80.65ETB / hour | |
| Aluminium workerLabour by trade · LabourSource: PDF p. 51 ↗ | 180.00ETB / hour | |
| Aluminium worker assistantLabour by trade · LabourSource: PDF p. 51 ↗ | 81.89ETB / hour | |
| Mud workerLabour by trade · LabourSource: PDF p. 51 ↗ | 81.29ETB / hour | |
| Truck 16 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 7,009.20ETB / hour | |
| Truck 9 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 2,560.36ETB / hour | |
| Truck 13 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 3,251.20ETB / hour | |
| CompactorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 678.05ETB / hour | |
| Wheel loader 200 HP (1.5–2.5 m³)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 6,297.13ETB / hour | |
| Dozer 300 HP (D7R)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 9,610.35ETB / hour | |
| Dozer D7R with ripperEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 10,060.35ETB / hour | |
| Dozer (200–250 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 8,867.34ETB / hour | |
| Excavator (200 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 8,560.35ETB / hour | |
| Excavator (200 HP) with ripperEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 9,131.04ETB / hour | |
| Backhoe excavator (120 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 6,560.35ETB / hour | |
| Grader (120–150 HP)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 7,560.35ETB / hour | |
| Roller (8–10 ton)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 4,304.60ETB / hour | |
| Water truck 13,000 litresEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 4,195.20ETB / hour | |
| Air compressorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 3,657.34ETB / hour | |
| Hand jack hammer (electrical)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 264.00ETB / hour | |
| Wagon drillerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 9,465.22ETB / hour | |
| Small vehicle (pickup 4WD)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 1,251.54ETB / hour | |
| Asphalt distributorEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 5,166.50ETB / hour | |
| Stationary heaterEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 3,451.86ETB / hour | |
| Power broomEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 2,380.24ETB / hour | |
| Asphalt plantEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 51,858.19ETB / hour | |
| Asphalt paverEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 11,433.22ETB / hour | |
| Pneumatic rollerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 4,133.65ETB / hour | |
| Water tankerEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 38.05ETB / hour | |
| Dump truck 16 m³Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 2,784.53ETB / hour | |
| Crushing plant 75 tonEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 19,952.80ETB / hour | |
| Centrifugal water pumpEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 499.85ETB / hour | |
| Generator (45 kW)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 935.89ETB / hour | |
| Mobile craneEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 7,609.20ETB / hour | |
| Concrete mixer (300 litres)Equipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 519.22ETB / hour | |
| Concrete mixer truckEquipment & machinery rental · EquipmentSource: PDF p. 52 ↗ | 3,098.82ETB / hour | |
| Concrete vibratorEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 266.09ETB / hour | |
| Hand tamperEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 110.47ETB / hour | |
| Pipe mouldEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 24.85ETB / hour | |
| Painting machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 1,253.57ETB / hour | |
| Hand drillEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 20.71ETB / hour | |
| Gear machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 34.52ETB / hour | |
| GrinderEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 34.52ETB / hour | |
| Cutting disc (diameter 180)Equipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 162.00ETB / hour | |
| ScaffoldingEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 117.60ETB / hour | |
| Sledge hammerEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 6.28ETB / hour | |
| ToolsEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 14.40ETB / hour | |
| Set of toolsEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 22.80ETB / hour | |
| Surveying instrumentEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 129.24ETB / hour | |
| Welding machineEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 101.20ETB / hour | |
| Hydraulic truck crane, 20–25 tonEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 5,383.58ETB / hour | |
| Winch 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 251.04ETB / hour | |
| Winch single phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 188.28ETB / hour | |
| Generator 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 502.08ETB / hour | |
| Generator single phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 313.80ETB / hour | |
| Generator for winch 3-phaseEquipment & machinery rental · EquipmentSource: PDF p. 53 ↗ | 403.92ETB / hour | |
| Local Grade 75 rebar work, 6 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.97ETB / kg | |
| Local Grade 75 rebar work, 8 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 242.06ETB / kg | |
| Local Grade 75 rebar work, 10 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 242.06ETB / kg | |
| Local Grade 75 rebar work, 12 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 14 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 16 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 20 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 24 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 32 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 238.74ETB / kg | |
| Local Grade 75 rebar work, 6 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 249.12ETB / kg | |
| Local Grade 75 rebar work, 8 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 249.12ETB / kg | |
| Local Grade 75 rebar work, 10 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 249.12ETB / kg | |
| Local Grade 75 rebar work, 12 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Local Grade 75 rebar work, 14 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Local Grade 75 rebar work, 16 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Local Grade 75 rebar work, 20 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Local Grade 75 rebar work, 24 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Local Grade 75 rebar work, 32 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 241.72ETB / kg | |
| Imported Grade 75 rebar work, 8 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 252.12ETB / kg | |
| Imported Grade 75 rebar work, 10 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 252.12ETB / kg | |
| Imported Grade 75 rebar work, 12 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 14 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 16 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 20 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 24 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 30 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 32 mm — SubstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 243.89ETB / kg | |
| Imported Grade 75 rebar work, 8 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 260.35ETB / kg | |
| Imported Grade 75 rebar work, 10 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 260.35ETB / kg | |
| Imported Grade 75 rebar work, 12 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Imported Grade 75 rebar work, 14 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Imported Grade 75 rebar work, 16 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Imported Grade 75 rebar work, 20 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Imported Grade 75 rebar work, 24 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 251.95ETB / kg | |
| Imported Grade 75 rebar work, 30 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Imported Grade 75 rebar work, 32 mm — SuperstructureReinforcement work · WorksSource: PDF p. 15 ↗ | 246.87ETB / kg | |
| Galvanized EGA 300 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,596.25ETB / m² | |
| Galvanized EGA 300 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,785.51ETB / m² | |
| Galvanized EGA 300 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,958.45ETB / m² | |
| Galvanized EGA 300 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,135.55ETB / m² | |
| Galvanized EGA 300 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,385.35ETB / m² | |
| Galvanized EGA 300 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,632.49ETB / m² | |
| Galvanized EGA 300 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,863.96ETB / m² | |
| Galvanized EGA 300 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,107.64ETB / m² | |
| Galvanized EGA 400 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,780.73ETB / m² | |
| Galvanized EGA 400 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,987.74ETB / m² | |
| Galvanized EGA 400 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,217.70ETB / m² | |
| Galvanized EGA 400 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,430.31ETB / m² | |
| Galvanized EGA 400 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,623.64ETB / m² | |
| Galvanized EGA 400 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,847.72ETB / m² | |
| Galvanized EGA 400 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,071.13ETB / m² | |
| Galvanized EGA 400 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,264.50ETB / m² | |
| Galvanized EGA 500 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,846.07ETB / m² | |
| Galvanized EGA 500 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,116.70ETB / m² | |
| Galvanized EGA 500 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,300.15ETB / m² | |
| Galvanized EGA 500 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,523.61ETB / m² | |
| Galvanized EGA 500 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,731.78ETB / m² | |
| Galvanized EGA 500 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,935.84ETB / m² | |
| Galvanized EGA 500 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,213.53ETB / m² | |
| Galvanized EGA 500 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,488.80ETB / m² | |
| Galvanized EGA 600 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,915.24ETB / m² | |
| Galvanized EGA 600 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,110.72ETB / m² | |
| Galvanized EGA 600 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,313.65ETB / m² | |
| Galvanized EGA 600 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,543.02ETB / m² | |
| Galvanized EGA 600 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,756.42ETB / m² | |
| Galvanized EGA 600 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,977.88ETB / m² | |
| Galvanized EGA 600 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,263.52ETB / m² | |
| Galvanized EGA 600 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,584.72ETB / m² | |
| Galvanized EGA 700 roof cover, 0.30 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,997.42ETB / m² | |
| Galvanized EGA 700 roof cover, 0.35 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,153.62ETB / m² | |
| Galvanized EGA 700 roof cover, 0.40 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,329.62ETB / m² | |
| Galvanized EGA 700 roof cover, 0.50 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,631.07ETB / m² | |
| Galvanized EGA 700 roof cover, 0.60 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,765.22ETB / m² | |
| Galvanized EGA 700 roof cover, 0.70 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,988.52ETB / m² | |
| Galvanized EGA 700 roof cover, 0.80 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,289.92ETB / m² | |
| Galvanized EGA 700 roof cover, 1.00 mm (includes J-bolt)Roofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 3,601.22ETB / m² | |
| EGA 0.4 mm (G28) coated roof coverRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,929.94ETB / m² | |
| EGA 0.4 mm (G28) coated wall coverRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,754.90ETB / m² | |
| EGA 0.4 mm (G28) coated wall with 10 cm vertical and 6 cm horizontal eucalyptus membersRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 2,022.07ETB / m² | |
| Galvanized gutter G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 821.83ETB / linear m | |
| Galvanized gutter G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 750.07ETB / linear m | |
| Galvanized gutter G28, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 968.35ETB / linear m | |
| Galvanized gutter G30, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 864.31ETB / linear m | |
| Galvanized gutter G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,157.05ETB / linear m | |
| Galvanized gutter G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 920.41ETB / linear m | |
| Galvanized gutter G28, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,332.49ETB / linear m | |
| Galvanized gutter G30, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,051.99ETB / linear m | |
| Galvanized gutter G28, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,470.71ETB / linear m | |
| Galvanized gutter G30, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 18 ↗ | 1,299.85ETB / linear m | |
| Galvanized downpipe G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 854.07ETB / linear m | |
| Galvanized downpipe G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 854.07ETB / linear m | |
| Galvanized downpipe G28, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,012.90ETB / linear m | |
| Galvanized downpipe G30, developed length 40 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 857.70ETB / linear m | |
| Galvanized downpipe G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,077.46ETB / linear m | |
| Galvanized downpipe G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,044.66ETB / linear m | |
| Galvanized flashing G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,082.14ETB / linear m | |
| Galvanized flashing G30, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,192.91ETB / linear m | |
| Galvanized flashing G30, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,497.41ETB / linear m | |
| Galvanized flashing G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,264.84ETB / linear m | |
| Galvanized flashing G28, developed length 67 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,472.74ETB / linear m | |
| Galvanized flashing G28, developed length 100 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,590.48ETB / linear m | |
| Galvanized capping G28, developed length 25 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 620.78ETB / linear m | |
| Galvanized capping G30, developed length 25 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 615.68ETB / linear m | |
| Galvanized capping G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 856.77ETB / linear m | |
| Galvanized capping G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 616.70ETB / linear m | |
| Galvanized capping G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 865.58ETB / linear m | |
| Galvanized capping G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 824.78ETB / linear m | |
| Galvanized roof ridge G28, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 759.81ETB / linear m | |
| Galvanized roof ridge G30, developed length 33 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 657.81ETB / linear m | |
| Galvanized roof ridge G28, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 889.35ETB / linear m | |
| Galvanized roof ridge G30, developed length 50 cmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 792.45ETB / linear m | |
| PVC downpipe PN4, 75 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 469.41ETB / linear m | |
| PVC downpipe PN4, 110 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 567.84ETB / linear m | |
| PVC downpipe PN4, 160 mm diameterRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,019.08ETB / linear m | |
| G28 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,370.13ETB / m² | |
| G30 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,229.59ETB / m² | |
| G32 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 997.16ETB / m² | |
| G35 corrugated iron sheet roof work, without truss and purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 833.46ETB / m² | |
| Aspesto roof cover with all necessary works (source wording)Roofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 847.68ETB / m² | |
| Euro tile roof cover with all necessary worksRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 878.88ETB / m² | |
| Grass roof cover with all necessary worksRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 825.13ETB / m² | |
| Transparent fibre roof cover, corrugated, 2 mmRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,257.17ETB / m² | |
| G32 CIS roof with Shashemene Zigba purlin (4 × 5 cm)Roofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,412.24ETB / m² | |
| Tsid timber cladding, 1 cm, for decorating roof purlinRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 1,453.56ETB / m² | |
| Lightweight concrete 1:2:5 for roofRoofing & rainwater goods · WorksSource: PDF p. 19 ↗ | 15,754.06ETB / m³ |
Try another search, or open the complete original category tables below.
Complete source tables
Every category includes its original PDF pages. Search and estimates use visually checked transcriptions; additional work rates remain available in the full source tables.
Your reference estimate
Add a checked rate with the + button. Quantities use the exact unit shown.
Your estimate is empty. Add materials or work items above.
Before you use a rate
Are these current Conmart selling prices?
No. They are rates from the supplied Addis Ababa construction cost document for 2018 E.C. Q4. Request a current quote for availability, brand, specification and delivery terms.
Does “2018” mean Gregorian 2018?
The document uses the Ethiopian calendar and identifies the 2018 E.C. fourth quarter. The cover letter is dated 30/10/2018 E.C. The original period is retained to avoid confusion with Gregorian years.
Are VAT and transport included?
PDF page 49 explicitly says material selling prices are without VAT. Its note includes loading, unloading and transportation. Do not automatically apply that note to every work or hire rate. Confirm the relevant scope and tax treatment in your supplier quotation.
What is the difference between supply and work rates?
The material table gives local Grade 75 rebar at 200 ETB/kg. The separate reinforcement work table gives rates by diameter and structure. Similarly, roofing work per m² is different from a roofing sheet sold per running metre.
How should I read the units?
One quintal is 100 kg. m² means square metre; m³ means cubic metre; linear m means running metre. Labour and machinery tables are hourly. Preserve the source unit when entering quantities.
Why do some categories open original tables?
The source is scanned. Checked transcriptions are searchable and available for estimates. The complete source pages preserve all remaining rates, specifications and qualifications without publishing unverified OCR numbers.